To request isolation of Low Voltage or High Voltage Switching on our network, please complete the below form. A quotation will be prepared and sent to you for approval before we'll action your switching request.
IMPORTANT: Please allow a minimum of 20 business days from the date of this request to schedule switching activities. Timeframes may be extended where third parties are required to be engaged.
Switching is a process where our network substations or transformers may need to be ‘switched off’ or so that supply to a particular premises is ‘isolated’ from the network. This is done when a customer needs to conduct works at the property, e.g. upgrading a switchboard, upgrading supply, upgrading or replacing customer mains.
Switching may also be known as Isolation Upstream.
Switching includes:
For specific examples, please refer to the below table.
Refer to our Customer Switching Guide (PDF 1.3 mb) for the requirements for switching requests.
If you have further queries, please contact the Electrical Contractor Hotline 1800 237 466 (Monday to Friday, 7:00am - 5:00pm).
Please view our privacy statement regarding the collection of data.
NOTE: In some cases, a Connect Agreement and an EWR may be required in addition to the below. Contact the Electrical Contractor Hotline on 1800 237 466 for more information.
Required fields are marked with an asterisk (*).
Under the Electrical Safety Regulation 2013 (section 209) you must notify us before works start on any construction, addition or other work on a building or structure that is likely to come within the regulated clearance requirements under the Electrical Safety Regulation 2013 (part 5) for an overhead or underground electric line. You can notify us by submitting this form or by calling us. Any reasonable costs associated with required relocation or modification of our assets will be at the cost of the responsible person.