Rows of electrical switches in a switchboard
You’re seeing information for
Greater Queensland
Not on the right website?
Go to the Energex website

Electrical contractor updates

Keep informed about what's happening in the industry and any changes to compliance, rulings and legislation. Subscribe to receive our Electrical Contractor Update newsletter!

If you have any queries you can email us or call the Contractors Hotline on 1800 237 466.

2024 updates

TopicsDate of issue
Energy Academy 2024; Provision of DNSP service and connection points for lots with abutting structures; New IVR Options for the EC Hotline31 October 2024
Network Load Capacity Maps; Meter Isolation Links; Update to Authorised Person - Electrical approval process26 September 2024
Update to Australian Standard clears the road for V2B and V2G connections in Queensland; Common Queries for the Electrical Contractors Hotline; Electrical Work Requests – Timeframes and Required Information29 August 2024
QEMM Transition Period Ending August 2214 August 2024
Labelling of Consumer Mains Reminder; Low Voltage Embedded Generation Fees increasing from 1 August 202409 July 2024
If You Install Electrical Vehicle Supply Equipment - You Could Win 1 of 4 $250 Gift Cards;  EWR Secondary Service Selection – Drop and Re-erect Service;  Continuing Professional Development and Dynamic Connections;  Information to Support You Installing Electric Vehicle Supply Equipment27 June 2024
Embedded Generation Applications and Batteries; Decommissioning Inverters After Firmware Upgrade; Non-domestic Meter Board Locations; Accurate Information for Connection Applications30 May 2024
Point of Attachment Approved Listing Available Now; New Dynamic Connections Web Content and Factsheet; Electrical Contractors Hotline – Reporting Faults Reminder; Name Change for LV Generation Team; Unlawful and Unsafe Electrical Work Practices Reminder24 April 2024
Reminder for Solar and Renewables within an Embedded Network; Negotiated Connection Contract Charges Reminder28 March 2024
Version (4) of the Queensland Electricity Connection Manual (QECM); New Electric Vehicle Supply Equipment Charging Options; Changes to Customer Requested Switching; Electrical Plant Information on Connection Applications; Reimbursement of Electrical Contractor fees29 February 2024
QECM Engagement Roadshow Schedule Updated; Changes to Submission of Electrical Contractor Fee Reimbursements; New Home for Standard Work Procedures and Technical Documents31 January 2024

Last year

UpdateTopicsDate of issue
Issue 18Queensland Electricity Connection Manual Engagement Roadshows; Decommissioning of Electrical Contractor Fees inbox; Dynamic Connections Update21 December 2023
Issue 17Electrical Contractor’s Hotline New Interactive Voice Response (IVR) Options; Information to Help Progress Your Connection Application30 November 2023
Issue 16Electrical Partners Portal troubleshooting; LV Generation applications; Asbestos Containing Material in metering panels; Dynamic Connections update26 October 2023
Issue 15Win a gift card; Call Back Request Form; EWR Notifications; Defect Form Name; Connection Application Fees; Emergency Backstop Mechanism Inspections28 September 2023
Issue 14Timeframe changes; New websites; Dynamic Connections Update17 August 2023
Issue 13LV Embedded Generation Fees increasing 1 September 202328 July 2023
Issue 12Expedited LVCT Metering Advice Fee Increasing 1 September 2023; Electrical Safety Week 4 - 8 September 202327 July 2023
Issue 11Extended consultation for Queensland Electricity Connection Manual (QECM)13 July 2023
Issue 10Energy Academy invitation; Supply abolishment with assets on site; New connections not yet ready; Retirements of existing solar email address; Dynamic connection update; CTS Certificate of Supply28 June 2023
Issue 09Consultation open for the Queensland Electricity Connection Manual (QECM) - Closes 14 July 202320 June 2023
Issue 08Remove Meter – Additional Service Request; Embedded Generation Application Reminder - Understand our Standards and Connection Policy; Dynamic Connection Update; Win a $100 Gift Card!25 May 2023
Issue 07Working with Asbestos; LV Current Transformer Metering Installation Design Requests; Micro EG Units Being Switched on Before Metering Has Been Installed or Reprogrammed; Existing NMI Supply Abolishment Process Reminder5 May 2023
Issue 06Emergency Backstop Mechanism Update3 April 2023
Issue 05Getting Reconnected After Storm Damage, Flooding, or Inundation; Contractor Hotline & Enquiries and Applications - Providing Correct Customer Details30 March 2023
Issue 04Network voltage; When is an EWR required for a meter reseal; Supply upgrades in conjunction with POA relocations23 February 2023
Issue 03Changes to LV Generation Standards Effective Monday 6 February 20236 February 2023
Issue 02Tips and tricks for a compliant Connection Application25 January 2023
Issue 01Submitting Connect Agreement or EWR on repair of privately owned line defects & Emergency Backstop implementation10 January 2023

Archived updates

If you are looking for older editions of our Electrical contractor updates, please email us.