Crew member in a cherry picker working on overhead wires with houses in background

March 2025

Updated Compliance Report templates for generating systems over 30kVA

With the release of the latest version of the Embedded Generating Connection Standards, we have also released the updated Compliance Report templates for generating systems over 30kVA.

The Compliance Report templates now require additional information demonstrating emergency backstop compliance including requiring photos of the installation. Please ensure you have reviewed the requirements of the updated form before heading to site.

The updated Compliance Report templates can be accessed via our network websites:

View all Electrical Partners Alerts

Keep informed about what's happening in the industry and any changes to the installation process, compliance, rulings and legislation.